Hassan Muheisen
ANIS (Amman Network Information System) is part of a corporate GIS project at WAJ. The introduction of computerised, partly GIS based business applications in Greater Amman, resting on different platforms and spread over more than 10 locations is illustrated on the example of the new Customer Complaints Centre (CCC), developed under ORACLE, and integrated with the front-end, ARCVIEW based Maintenance Management System (MMS), both related and exchanging information with the ANIS core unit, responsible for maintenance, updating and editing of all network and cadastral maps under ARCINFO. The maintenance of GIS database systems, combining ARCINFO/ARCVIEW and ORACLE environments requires not only integration, but as well data integrity between GIS features and RDBMS data on the ORACLE side .CCC & MMS have been introduced in an environment not accustomed and susceptible to such complex systems, but the success of modules like MMS in the daily work process illustrates, that user/friendly applications are immediately accepted and useful on all hierarchical levels of WAJ .

The most pressing needs and priorities of WAJ in the ANIS implementation were
ANIS/OMS took the challenge and started development of an integrated concept, consisting of pure database applications for the country wide service and a combined GIS/ ORACLE database environment for Greater Amman area .
This approach had to be taken as digital cadastral maps are only available for Greater Amman area, but not for the rest of the country.
The function of each subsystem is described as follows.
The Customer Complaints Centre System (CCC) was developed under ORACLE and integrated with the front-end, ARCVIEW based Maintenance Management System (MMS), both related and exchanging information with the ANIS (Amman Network Information System) core unit which is responsible for updating and editing of all network and Cadastral maps under ARCINFO.
The overall integration of ANIS , MMS and CCC is shown in below:

The Complaints Center CCC will receive, dispatch, monitor and follow up the customer complaints for the whole country .The basic concept of the center is focused on improving the customer oriented services, accuracy & transparency enables closed integrated information cycles, speed up response time ,monitoring & control of the different functions. The customer is neither interested nor has the will to find out the responsible WAJ unit for his request or complaint. In this respect, the CCC acts as a liaison between the customer and WAJ line functions ,therefore according to the information taking from the customer , CCC is programmed to dispatch the complaints automatically to the concerned WAJ unit. The following screen shows main data entry screen of CCC.

The Centre accepts customer complaints that are related to the water network (i.e. pipe burst, no water, realignment of water pipes), sewerage network complaints, illegal water consumption, no bill delivered to customer and water quality related complaints .These complaints are stored on the database and the complaint information transfer from CCC to the various divisions and vice versa can be done using the conventional way (i.e. fax or fax modem card) or by means of electronic information transfer in the cases where MMS exists, with ArcView reading the complaints directly from the Oracle server in the Centre through telephone line / TCPIP protocol and ODBC drivers
MMS is an ANIS integrated, operational front end system intended to support all Maintenance Divisions in efficient planning, monitoring and execution of repair services. The system allows the Maintenance Division to
MMS further provides valuable information to WAJ management in respect of targeted investment planning, management contract monitoring / control and customer services.
All of the maintenance activity data is stored in database form. However, most of the functions of MMS are accomplished using customized Arcview GIS software. The system is closely integrated with the Oracle based Customer Complaints Center (CCC) at the Ministry.
The following screenshot shows work order sheet of MMS application.

The communication between the MMS & CCC applications will be through Modems connected to telephone lines, MMS user will log in to CCC through SqlNet / TCP/IP and ODBC driver, once it is linked to the CCC Oracle, MMS imports the table which contains the total no of received complaints. MMS user then generate the work orders to start the repair action, when it is completed MMS user will send a feedback message by MMS Oracle through dial-up connecto CCC Oracle to close the cycle.

The MMS at the maintenance was developed for end users without background and knowledge about computers. After an initial training of existing staff at the Maintenance Division and after a test period, the speed of the response and the quick production of work order sheets was tested in various configurations .
The implementation had to consider the existing procedures and started at the maintenance division level, as all complaints in respect of leaks and no-water were received there.
MMS was installed in Sep 98 at Ras el-Ain maintenance division first, tested for 3 months, evaluated and necessary modifications to the application made.
On March 99, Ain Ghazal maintenance division was added as the second location, total no. of customer covered are about 120.000, only 4 PCs were needed, no additional staff employed. Intelligent programming allowed the use of relatively low end hardware (166MHz), still achieving fast response & performance.
CCC had to be established in the Ministry of water and irrigation, the 5 PCs + 1 server were installed in Dec. 98. The needed personnel requirements delayed the actual start of the system to Mid February 1999.
The table below shows some key data of MMS/CCC implementation
Description |
MMS |
CCC |
Evaluation Period |
1/11/1998 - 18/2/1999 ( Ras El-Ain ) |
20/2/1999 - 17/4/1999 (Ministry of Water & Irrigation) |
Total no. of complaints |
2187 complaints |
1373 complaints |
Daily Distribution |
Average 35 complaint per day |
Average 30 complaints per day |
Received / Completed |
2187 Complaints Received / 2177 completed |
1373 Received / feedback from Main. Div. 1094 |
Software |
|
|
Hardware |
2 computers with following specs:
|
3 Computers with the following specs:
|
Personnel |
|
|
A total no. of 2187 complaints were received during the test period.
The evaluation yielded very positive results and fully justifies the implementation of MMS in all AGWA maintenance divisions, as:
A second evaluation test for MMS application was done within the last two weeks to monitor the acquaintance of the staff with and stability of the system. For two weeks the data entry staff were working with MMS without any technical problems and outside assistance. The performance of the staff was very good, all complaints were entered to the computer, updates of landmarks and street names done which indicates the stability of the system.
The table below shows the Comparison Between Old and New Procedures
| Item / criteria | Old Procedures | New Procedures |
| TIME Time needed to locate a complaint Time needed to Print work order sheet Time needed to prepare work order sheet |
15 Minutes Not Available 30 minutes per team (10 complaints average) |
30 seconds 30 seconds 10 minutes per team |
| Accuracy of Complaints location Inside selected Box Inside the sheet outside sheet |
- - - |
90% 97% 3% |
| Response Time 0-6 hours 6-12 hours 12-24 hours 24-48 hours > 48 hours |
Not available on hourly bases |
20% 20% 50% 7% 3% |
| Performance of the teams Follow-up, checking & monitoring of WOS Updating of landmarks, street names & house connection on sheets Monitoring of quality
Map Location Preparatory of work |
No sheets are available Not Available
No criteria
takes long time takes long time (90 minutes) |
30 sheets per day 10 sheets per team
Quality was improved by checking of each sheet Random check on the field Analysis of data Takes less time Takes less time (30 minutes ) |
The system was not in operation for long but some results already prove the usefulness, but hint as well towards some bottlenecks:
Total no of 1373 complaints received and entered onto CCC Database as follows between February & March 1999:
Month / Year |
Total No. Of Complaints Received |
No water |
Broken Line/Leak |
Sewerage |
Illegal Water Usage |
Water Bill Not Received |
Water Quality |
Feb/1999 |
67 |
17 |
44 |
2 |
2 |
2 |
0 |
Mar/1999 |
784 |
366 |
390 |
7 |
7 |
13 |
1 |
Apr/1999 |
522 |
209 |
302 |
2 |
6 |
2 |
1 |
.
Feed Back / Status of Complaints received from Maintenance divisions |
Total No. of Complaints with respect to maintenance division from Midd Feb - Apr 1999 |
|||
Status |
Total No. Of Cases |
Maintenance Division |
Total Complaints Received |
|
Pending |
34 |
Ein Ghazal maintenance division |
374 |
|
Line is Fixed |
475 |
Ras Ein maintenance division |
169 |
|
Water Reached to the location |
383 |
North Amman maintenance division |
80 |
|
To be observed in the next pump period |
36 |
West Amman maintenance division |
88 |
|
Transferred to other maintenance division |
64 |
Control Division/AGWA |
434 |
|
Complaints types already received from the same address |
39 |
Sewerage maintenance Division |
13 |
|
Address not clear |
47 |
Subscriber division / South Amman |
7 |
|
Illegal water usage |
3 |
Maintenance Division / South Amman |
181 |
|
There is No Illegal usage |
2 |
Water Resources |
2 |
|
Water bill delivered to the subscriber |
7 |
Subscriber Directorate/ AGWA |
25 |
|
Water bill will be issued |
2 |
|||
Sewer flooding due to rain water |
1 |
|||
No Pollution observed |
1 |
|||
The easy use and the extremely positive results allow implementation of the MMS on country wide level within a short time period of only one year. The intensive preparation through detailed workstudies, organisational changes snd the tight integration to the business process are the basis of success.
The maintenance management system had its roots on the leak repair team workstudies done by WAJ-OMS which exposed the deficits and shortcomings of the maintenance management & operations. Its further successful implementaiton was only possible through the engagement of the Ain Ghazal Maintenance Division and its Head, Eng. Abdelkarim Naji.
Hassan Muheisen
ANIS Remote Sites Manager, Water Authority of Jordan, PO Box 830752 Amman, Tel.
(962-6-5925731), (962-6-5666111, ext. 131), E-mail:
Hassan_Kiswani@pmuoms.index.com.jo